News

Onboard and Online: A303 Stonehenge – The DCO Inspection Begins

The preliminary meeting of the Planning Inspectorate inspection team took place at Salisbury Racecourse on 2nd April 2019. It was attended by two members of the Parish Council and a number of villagers representing organisations and/or themselves. As a preliminary meeting, its purpose was to introduce the inspection team, but mainly to outline the process that was to be followed and the timelines involved. As meetings go, the best thing that can be said about it was that it was a turgid affair, most people don’t get too excited by process…

The most depressing thing was that by lunchtime, the word that had barely been mentioned, if at all, was ROAD. What we had heard about in excruciating detail was the archaeology. It’s quite clear, if ever there was any doubt, that more time is going to be devoted to the (claimed) interests of the long-dead than the interests of the living and generations yet to be born.

Anyone wishing to read or listen to an account of that first meeting can do so on the Planning Inspectorate website, here. A certain cure for insomnia.

All the submissions to the Planning Inspectorate on the Development Consent Order can be found on their A303 Scheme web pages. The best starting point is here. This will give you links to the DCO Examination Timetable, documents that have been submitted to the Inspectors and what they call Relevant Representations. There are already over 400 documents logged, some of which run into hundreds, if not thousands of pages. There are also over 200 Relevant Representations. We, like you, are going to have to be selective in what we read, or respond to. We know, already, that we may miss things, so please let us know if there are issues you think the Parish Council need to respond to.

Please understand that there is so much information being generated that we are simply not able to capture it all for you and reproduce it here. The only things we intend to put on the website are those documents generated by the Parish Council. Of course, circumstances may dictate otherwise. We will however, publish “sound bites” from time to time to give you an idea of progress or otherwise.

The next deadline we have to meet is the 3rd May. By then we will have delivered a Written Representation to the Inspectors and a reply to a question that the Inspectors have addressed to the Parish Council. These were based on the points raised in our previous responses, both non-statutory and statutory, to the Highways England Consultation. Councillors agreed to combine their response with that of the Chairman, as both were going to be very similar, the extremely scientific nature of some of the issues and to prevent duplication and unnecessary effort. Where their were differences, the agreed view of the Parish Council had primacy

We will be represented at the Open Floor Hearings during the first session on 22nd May from 10:00am – a brief 5 minute slot at most. It’s an opportunity to highlight some of the bigger issues that will affect the village in perpetuity.

We will continue to represent the Parish at a series of meetings and workshops over the next few months. We also anticipate that the Inspectors may address further questions in our direction. In other words, there is an awful lot of activity going on in which we are all involved. It’s going to be a long summer.

If you are aware of neighbours who don’t have access to the Internet at home, or read the village noticeboard, please can you let them know that access to the Internet is available at Amesbury and Salisbury libraries, where they can access this website at: https://winterbournestokepc.org.uk and the Planning Inspectorate pages at: https://infrastructure.planninginspectorate.gov.uk/projects/south-west/a303-stonehenge

Winterbourne Stoke Parish Council